Merlin – Handling scheduling warnings and conflicts

SchedulingConflictsWhen planning your project with Merlin on your Mac, there might be scheduling warnings or conflicts.

Warnings
Warnings are shown when a specified value has been exceeded. A warning does not necessarily mean that your project plan contains an error. It can certainly be intended. For example, an activity starts or ends in a work-free period.It is possible to deactivate the warnings in the Activities View Options. Possible warnings are:
  • Activity starts at a non-working time
  • Activity ends at a non-working time
  • Planned work exceeds the given value
  • Expected work exceeds the given value
  • Planned duration exceeds the given value
  • Expected duration exceeds the given value
  • Budget sum exceeds approved budget
Conflicts
A conflict indicates a problem Continue reading